To qualify for NEM 2.0, you will need to have the following submitted by 11:59 p.m. April 14, 2023.
- Completed application, free of major deficiencies (i.e. no blanks, incomplete/inaccurate document, changes requiring resubmission per Rule 21)
- A single-line diagram
- A signed CLSB Disclosure and Solar Consumer Protection Guide (For residential, non-self install only)
- A signed Agreement and Authorization Form (For Standard NEM only)
- A final inspection clearance must be submitted before 04/15/26 to retain NEM2 eligibility
NOTE: Your application does not have to be approved by PG&E by this date nor do your panels need to be installed by this date. To ensure your application will be deemed complete, we advise you to submit your application as early as possible.